ASM - Can the generation of ASM Enrichment policies be scheduled?

Last Updated: Jul 14, 2017 12:26PM UTC
Yes, ASM Enrichment policies can be scheduled if you are running SCM version 1.3.32.25w of higher.

Note: The Interlink Software Data Service must be running for scheduled tasks to run.

To schedule the generation of an ASM Enrichment policy, perform the following:
 
  1. Open SCM and click View > Scheduler Calendar.
  2. Select a day of the month you would like the enrichment to be generated on (if you want it to run every day, simply select any day in the calendar).
  3. Once you have selected a day, right click on a time slot on the right hand side, then select Task > New Task.
  4. Enter the task details, such as a Name, Time, Description etc. Then select 'Run Enrichment' from the Task drop down list.
  5. Select an enrichment policy to generate (Argument 1).
  6. Select a BES Server (defined export) to generate the policy on (Argument 2).
  7. Click on the Recurrence tab and select how often the task should run.

An example of an Enrichment Scheduled task is below (Generate enrichment policy "ENR_Zone_Enrichment" at "20:00" every day on BES server "vmdemobes04"):


Contact Us

desk.com@interlinksoftware.com
https://cdn.desk.com/
false
desk
Loading
seconds ago
a minute ago
minutes ago
an hour ago
hours ago
a day ago
days ago
about
false
Invalid characters found
/customer/en/portal/articles/autocomplete